Project News / Schedule

Work Accomplished as of February 2012

We are pleased to report that the project is almost complete.
Thanks to the City of Woodland, Caltrans and Salaber Associates, Inc. the city now has:

  • A new southbound I-5 on-ramp.
  • The County Road 102 (CR-102) bridge has been widened to four lanes.
  • Modifications have been made to the northbound and southbound off-ramps and to the northbound loop on-ramp.
  • CR-102 has been widened to six lanes south of the interchange to Maxwell Avenue.
  • The southbound left-turn lane at Maxwell Avenue has been lengthened and widened to two lanes.
  • Community enhancements, such as new street lighting and landscaping, have been added.

Upcoming Work

Over the next month, the contractor will be performing minor repairs before the project can be considered complete. These repairs should not have any impact on the public.
Thank you for your patience during these final weeks of the project.

Due to the unseasonable weather that has occurred, the completion date of the project has been moved to late December or early January.